The track switch area

An additional site has emerged out of the construction works between the underground stations Rotes Rathaus and Museuminsel: the track switch area.  Up to March of 2016, this open trench excavation was the launching shaft for the tunnel boring machine Bärlinde; both of the tunnel tubes were started from here.  The main material storage area, nearby at Marx-Engels Forum, has served as the logistics center for the project as well, housing the offices of Implenia and the contractor Los 1 (tunnel, track switch area, Museuminsel, Unter den Linden).

© Antonio Reetz-Graudenz
What is a track switch area?

As the name says, the track switch area is where the trains can switch tracks.  It is important for operations because technical disruptions can be isolated, avoiding a complete shut down of the line. The two separate tunnel tubes between here and Brandenburger Tor make a switch before or beyond this point impossible. 

The track switch area also had another role as launching shaft for the tunnel boring machine.  One of its first challenges in tunneling here was in achieving a great difference of depth within a short distance.  The platform at the bi-level underground station Rotes Rathaus is only a few meters from the surface - a new storage track and reverse loop are on the lower level – and nearby is the deep river Spree, under which the tracks will run at a 4% grade.

© Reetz-Graudenz
The Process of Construction

The first excavation, done here in open trench fashion, was the launching shaft for Bärlinde's boring of the tunnel tubes.  Various remnants of the TBM's work had to later be removed, for example, the reaction frame, the shield cradle and temp ring segments, used to make high-precision adjustments at the beginning of operations. The next steps are concreting and reinforcing the floor, the load-bearing walls, and the intermediate ceiling. 

© Reetz-Graudenz
The Harbour Basin

A harbour basin was specially built at Marx-Engels Forum in the Spree to transport materials and the tunnel boring machine to and from the site.

In total, some 120,000 cubic meters of excavated sand and stone and other rubble accumulated during  excavation – enough to fill a million bathtubs!  These diggings were treated using bentonite suspension and transported by conveyor back to the Marx-Engels Forum, where solids and liquids were separated at a small plant.  The sand was loaded up and barged away on the Spree and the bentonite reprocessed and reused.  Water transport was the environmentally friendly option,  avoiding an estimated 12,000 lorry hauls by road.

© Stefke
Marx and Engels

To create space for construction at Marx-Engels Forum, sculptures of Karl Marx and Friedrich Engels were also transported away in September 2010, but to a temporary home only, and not so far.  The bronze gentlemen now stand a few meters northwest of the forum center, towards the Liebknecht Bridge, but contrary to their former position. The statues now face to the west, not eastward.

For now, the plans are to return Marx-Engels Forum back to its original state upon completion.  So Marx and Engels will once again be at center stage and presumably rotated back. However, the Berlin senate and Mitte burrough council are still pondering subtleties in the forum's overall future look.

© Martin Stefke